Time and Work — method, worked example and MCQ
EnglishCore method
Convert completion times to rates before adding. If A takes a days, A completes 1/a of the job per day. Choose an LCM-sized job to work with whole-number rates.
Worked example
A finishes in 10 days and B in 15. For a 30-unit job they complete 3 and 2 units per day. Together they finish in 6 days.
Practice MCQ
A and B can finish in 12 days together. A alone takes 20 days. How long does B alone take?
- 24
- 28
- 30
- 32 days
Answer C. B’s rate is 1/12 − 1/20 = 1/30.