🎯 Quiz Universe Login
👤
Welcome!
Login to access all features
Free Platform TNPSC Prep
Main Menu
🏠
Home
🎓
All Exams
📝
TNPSC
🔒
Paid Tests
🚆
RRB Exams
📖
TNPSC Study Module 24-WK
📊
Maths Tests
⚡
Maths Practice
💼
Job Alerts
📚
Study Notes
🗞️
Current Affairs
📄
Documents
📋
OMR Tests
🏆
Tournament LIVE
🥇
Leaderboard
👥
Study Groups
💬
Community
Account
🔐
Login
✏️
Register Free
Info
❓
Help & Support NEW
ℹ️
About Us
📬
Contact Us
🔒
Privacy Policy
📋
Terms & Conditions
⚠️
Disclaimer
📌
Topic

Time and Work

1 resource

Time and Work — method, worked example and MCQ

English

Core method

Convert completion times to rates before adding. If A takes a days, A completes 1/a of the job per day. Choose an LCM-sized job to work with whole-number rates.

Worked example

A finishes in 10 days and B in 15. For a 30-unit job they complete 3 and 2 units per day. Together they finish in 6 days.

Practice MCQ

A and B can finish in 12 days together. A alone takes 20 days. How long does B alone take?

  1. 24
  2. 28
  3. 30
  4. 32 days

Answer C. B’s rate is 1/12 − 1/20 = 1/30.